Williamstown Highway Department

 

Town Garage - 433-5571

Ed Farnham, Road Foreman
Jim Miller
Joe Perusse
Bryan Palmer
Ed Salls

Spring Highway Roads

***NOTICE***

EFFECTIVE IMMEDIATELY - Unless you have received prior approval from the Town Manager, NO overweight vehicles are to travel on Town highways. 

During the day call the Town Manager's Office - 433-6671 for roads that need attention. Most times during the day your call to the Town Garage will not have someone there to answer and you will get the answering machine. The road crew are out working on the roads.

After hours call the Town Garage at 433-5571 and leave a message. The Road Foreman will be checking the messages and alerting the road crew.

We continue to appreciate Residents feedback on road issues of concern by calling 433-6671, Town Manager's office or use the Contact Us on this site.

NO OVERWEIGHT TRUCKS ON TOWN HIGHWAYS DURING "MUD SEASON" CONTACT THE TOWN MANAGER'S OFFICE FOR FURTHER INFORMATION

 

6 Year Highway Plan

 

YEAR 1: 2014-2015

Graham Road ditching, culvert replacement, top dress

South Hill new culverts, channel drain installation,
Reconstruct

Winchester Hill Road ditching, top dress

Beckett Street install top paving coat .13 miles

Howe Street new pavement .04 miles

Seaver Road new pavement .34 miles

Depot Street New Storm drains, new sidewalk and new
Pavement .2 miles


YEAR 2: 2015-2016

South Hill continue reconstruction with 8” top dress

Falls Bridge Road channel drain and pave 1.4 miles from Route 14 to
Intersection of West Road

YEAR 3: 2016-2017

Hebert Road ditching, drainage, reconstruct with 8”top dress

Pleasant Street drainage by Shangraw’s residence

YEAR 4: 2017-2018

Hebert Road continue reconstruction with 8” top dress


YEAR 5: 2018-2019

Stone Road ditching, drainage, reconstruct and 8” top dress

YEAR 6: 2019-2020

Baptist Street ditching, drainage, reconstruct and 8’ top dress

High Street reconstruct